Scenario. Riverside Dental Clinics, a small chain in Ohio, is starting a project to introduce online appointment booking. The Project Manager, Daniel Hughes, wants to apply PRINCE2 in a way that is proportionate to the project.
| Project characteristic |
Riverside Dental Clinics: online booking project |
| Duration |
3 months |
| Budget |
$60,000 (internal funding) |
| Team |
4 staff from the clinic’s own IT department |
| Risk |
Low: proven booking software, one clinic location |
| Business owner |
Florence Grant, Operations Director, who also represents the clinic staff who will use the system |
Which is the
MOST appropriate way to tailor PRINCE2 for this project?
Select one option.