PRINCE2 Practitioner: Applying the People Practice
Question 1 of 5
Time left: 00:00
Free PRINCE2 Practitioner Q & A Practice 1 of 5 free Practitioner-standard exercises in this section
Scenario. Pinecrest Grocers in Georgia is installing self-checkout machines in 40 stores. The Project Manager, Sophie Turner, has mapped the main stakeholders.

Stakeholder analysis: new checkout system Keep satisfied Manage closely Monitor Keep informed Regional Director Store managers Cashiers Cleaning contractor Interest in the project Power / influence


The Regional Director can stop the rollout in her region but shows little interest in the project. Which engagement approach is MOST appropriate for her?
Select one option.