PRINCE2 Practitioner: Applying the Risk Practice
Question 1 of 5
Time left: 00:00
Free PRINCE2 Practitioner Q & A Practice 1 of 5 free Practitioner-standard exercises in this section
Scenario. The risk management approach for an HR system project at Silver Lake College in Utah states that threats are prioritized by risk score = probability × impact.

ID Threat Probability Impact
R1 Data center fire 2 5
R2 Key developer leaves 4 3
R3 Minor software bugs at go-live 5 2
R4 Late delivery of laptops 3 3
R5 Interface with payroll fails testing 4 4


Probability and impact (scale 1 to 5) 1 1 2 2 3 3 4 4 5 5 Probability (1 = very low, 5 = very high) Impact (1 = very low, 5 = very high) R1 R2 R3 R4 R5


Which threat should be given the highest priority?
Select one option.
You have used 0 of 1 attempt