Scenario. Summit Foods in Oregon is building a new e-commerce platform. A competitor has launched a similar service, so forecast sales benefits have fallen at each review. At the end of stage 2 the Project Manager presents the updated business case to the Project Board.

Review point Money already spent Cost still to spend Benefits still to gain
Initiation $0.2M $2.4M $3.2M
End of stage 1 $1.0M $1.6M $2.1M
End of stage 2 $1.8M $1.4M $0.9M


Forecast benefits still to be gained ($M) 0 0.5 1 1.5 2 2.5 3 3.5 3.2 Initiation 2.1 End stage 1 0.9 End stage 2 Business case review point Remaining benefits ($M)


Which is the MOST appropriate decision for the Project Board at this stage boundary?
Select one option.