✓Free PRINCE2 Practitioner Q & A Practice1 of 5 free Practitioner-standard exercises in this section
Scenario. The risk management approach for an HR system project at Silver Lake College in Utah states that threats are prioritized by risk score = probability × impact.
ID
Threat
Probability
Impact
R1
Data center fire
2
5
R2
Key developer leaves
4
3
R3
Minor software bugs at go-live
5
2
R4
Late delivery of laptops
3
3
R5
Interface with payroll fails testing
4
4
Which threat should be given the highest priority?