Scenario. The Department of Transportation in Tennessee is replacing a highway bridge. The project is heavily regulated and publicly funded. The Project Manager proposes the following tailoring.

Tailoring proposals: state highway bridge replacement A Remove the business case, because the state legislature has already approved the funding. B Add formal quality reviews with the state inspector for safety-critical products. C Use the state department's own document templates for all management products. D Align management stage boundaries with the regulator's approval gates. E Appoint a compliance officer to provide additional project assurance.


Which proposal is NOT acceptable tailoring?