Stakeholders, Communication and Knowledge Management
Question 1 of 5
Time left:00:00
✓Free PMP Q & A Practice1 of 5 free PMP exam-standard exercises in this topic
Larkspur Freight Co. is replacing its warehouse management system using a hybrid approach: a predictive rollout of scanners and hardware, and adaptive delivery of the software. After the kickoff, project manager Eleanor updated the stakeholder register and the power/interest grid below. The engagement assessment matrix sets the desired level for every stakeholder in the upper half of the grid at supportive or leading, and supportive for the shift supervisors.
Last week Eleanor met the operations director, whose resistance came from a fear of disruption during peak season; they agreed a cutover blackout window, he is now neutral, and a follow-up is already booked. The change-management lead is running the planned weekly floor sessions with the shift supervisors. Go-live cannot occur without written sign-off from the state fire inspector on the new rack and scanner layout, and nobody on the project has contacted his office yet. Eleanor has capacity for one new engagement action this week. Which action is MOST appropriate?