Scope, Requirements, Schedule and Delivery Planning
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Victoria manages a predictive project that is building a pharmacy dispensing system for a regional hospital network. The scope baseline was approved two months ago and construction is 40% complete. The compliance officer reports that a revised state regulation affects business requirement BR-05: patient records must now be retained for 7 years instead of 5, and the pharmacist countersignature must be captured before dispensing rather than within 24 hours. The sponsor emails Victoria: “This is mandatory, so just get it in.”

Business Linked requirement Work package, tests BR-05 dispensing FR-12 audit log status: built WP 3.2 TC-31, TC-32 FR-13 countersign status: in design WP 3.4 TC-35 NFR-04 retention status: built WP 4.1 TC-40 Excerpt of the requirements traceability matrix


What should Victoria do FIRST?
Select one option.