✓Free PMP Q & A Practice1 of 5 free PMP exam-standard exercises in this topic
Florence is the project manager of a predictive data-platform migration for a regional insurer. The go-live date is fixed by a regulatory deadline at the end of week 14. Eleanor, the only certified database architect, is shared with operations under a written agreement with her functional manager: 20 hours per week for the project, and operations will not release more during its quarter-close period (weeks 4 to 8). The resource histogram for Eleanor is shown. Activity P (schema migration) is on the critical path. Activity Q (index tuning) has a total float of 20 working days and a free float of 15 working days; both activities need Eleanor at 20 hours per week for three weeks and can only be done by her. The sponsor has suggested asking Eleanor to put in extra hours.