Resources, Procurement and Financial Management
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Florence is the project manager of a predictive data-platform migration for a regional insurer. The go-live date is fixed by a regulatory deadline at the end of week 14. Eleanor, the only certified database architect, is shared with operations under a written agreement with her functional manager: 20 hours per week for the project, and operations will not release more during its quarter-close period (weeks 4 to 8). The resource histogram for Eleanor is shown. Activity P (schema migration) is on the critical path. Activity Q (index tuning) has a total float of 20 working days and a free float of 15 working days; both activities need Eleanor at 20 hours per week for three weeks and can only be done by her. The sponsor has suggested asking Eleanor to put in extra hours.

Eleanor: planned project hours per week P: criticalQ: noncriticalR: review 010203040 12345678910week available 20 h


What should Florence do?
Select one option.
You have used 0 of 1 attempt
Next ▶