Quality, Value Delivery and Project Performance
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Charles is the project manager for a regional hospital's patient portal, delivered in a hybrid way: a fixed budget and governance gates, with the build done in two-week sprints. Beatrice is the Product Owner and is accountable for the backlog. The business case justified the portal mainly by a 30% cut in call-center volume through online appointment booking. Release 4, which delivered booking, went live six weeks ago. The remaining 12 features in the roadmap are messaging, bill payment and similar items. The sponsor has asked Charles for a status view, and the dashboard below was prepared.

Patient portal dashboard after release 4 Velocity (last 4 sprints) 32, 31, 33, 32 on plan Features released 18 of 30 on plan Budget used 55% on plan Online booking use 6% of patients target 40% Call volume reduction 4% business case 30% Top survey comment cannot find booking 41% of comments


What should Charles do FIRST?
Select one option.
You have used 0 of 1 attempt
Next ▶