Project Management Foundations, Delivery Approaches and Integrated Planning
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Harriet is the project manager for a predictive warehouse-automation project at Larkspur Freight Co. The Design phase has just finished and the Gate 2 review is scheduled for next week. Charles, the project sponsor, chairs the gate review board, and the PMO’s gate checklist covers only deliverable acceptance, cost and schedule. Yesterday the commercial team told Harriet that the largest customer, whose volumes made up 40% of the throughput assumed in the business case, will not renew its contract. A finance analyst re-ran the business case with the new volumes; the results appear on the dashboard below.

Warehouse automation: phase-gate plan Initiate Design Build Deploy G1 passed G2 next week G3 planned CPI 1.02 on budget SPI 0.98 within 5% Forecast NPV −$0.3M was $2.4M at G1 Design deliverables accepted: 14 of 14


What should Harriet do NEXT?
Select one option.
You have used 0 of 1 attempt
Next ▶