✓Free PMP Q & A Practice1 of 5 free PMP exam-standard exercises in this topic
Victoria is the project manager for an outpatient-scheduling project at a regional hospital, run as a balanced matrix. Her 14 team members come from Finance, IT and Clinical Operations, and each department judges its staff on its own goals. Recently, design decisions have stalled: Finance members push billing automation, IT members want a like-for-like replacement of the old system, and clinicians ask for changes that shorten patient waits. Last week the sponsor reconfirmed the objective in the project charter. Victoria then ran an anonymous pulse survey; the results are below.