Governance, Compliance, Organizational Change and Business Environment
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Victoria is the project manager for a predictive project that is replacing the billing system of a regional utility. The governance framework, summarized below, sets who decides on forecast cost overruns. At the latest monthly review her performance data is as shown in the table. Critical path analysis shows that the finish date will slip by 4 days, within her schedule variance threshold of 10 days, because most of the late work has float.

Governance and cost escalation thresholds Steering committee forecast overrun above 12% Sponsor (operations director) above 5% and up to 12% Project manager up to 5% of the budget PMO sets methods and reporting standards; no budget decision rights PMO standard forecast: EAC = BAC / CPI overruns are measured as a % of BAC


MeasureValue
Budget at completion (BAC)$3,200,000
Planned value (PV)$1,600,000
Earned value (EV)$1,280,000
Actual cost (AC)$1,400,000


What should Victoria do?
Select one option.