You manage a building-systems upgrade for a regional hospital. A new AI-enabled reporting tool produces the dashboard below for tomorrow's portfolio review.

Project dashboard, end of month 6BAC$2.0MPV$1.0MEV$0.8MAC$1.0MCPI by month1234560.80AI forecast (default)EAC $2.2MConfidence: highModel: portfoliohistory, 140 projects


Your root-cause analysis shows that the cost overrun comes from a new labor agreement whose higher rates apply to all remaining work. The sponsor has already accepted that the finish date may slip, so there is no fixed completion date. Which estimate at completion (EAC) should you report, and what should you do about the tool?