Agile, Adaptive and Hybrid Project Management
Question 1 of 5
Time left: 00:00
Free PMP Q & A Practice 1 of 5 free PMP exam-standard exercises in this topic
Larkspur Freight Co. is building a customer billing portal with Scrum, using Sprints of 10 working days. You are the Scrum Master. The Sprint Goal for Sprint 14 is: customers can pay an invoice by card in the portal. At the end of day 6 the Sprint burndown and the remaining Sprint Backlog are as shown.

Sprint 14 burndown, story points remaining010203040012345678910Sprint day (end of day)22 leftactualideal


Sprint Backlog itemPoints leftSprint Goal?
Card payment API7Yes
Payment error handling5Yes
Export invoices to CSV6No
Profile photo upload4No


At today's Daily Scrum the Developers explained that the card-payment integration was more complex than they expected. They have already re-planned their tasks for the last four days and confirm that their pace of about 3 points per day is realistic. The Product Owner, Florence, is in the office today. What should you do NEXT?
Select one option.