PRINCE2 Foundation: Progress Practice
Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
Study the graph for stage 2, at the end of week 5.

Stage 2 cost: budget $200,000 with tolerance of ±10% ($ thousands) 0 50 100 150 200 250 Wk 0 Wk 2 Wk 4 Wk 6 Wk 8 Wk 10 tolerance range at stage end upper tolerance $220k forecast $238k Planned spend Actual spend Forecast

What should the Project Manager do?
Select one option.