PRINCE2 Foundation: PRINCE2 Processes
Question 1 of 5
Time left:
00:00
✓
Free PRINCE2 Foundation Q & A Practice
1 of 5 free PRINCE2 Foundation-standard exercises in this section
Read the memo, which acts as the project mandate.
Memo from the Chief Operating Officer
“We need a new customer portal by next spring.”
“Matilda Grant will be the Executive. Please appoint a Project
Manager and confirm whether this is worth doing before we spend
serious money.”
Which process does this mandate trigger, and what is that process's purpose?
Select one option.
A
Initiating a Project: to establish solid foundations, including the PID.
B
Directing a Project: to authorize each stage.
C
Controlling a Stage: to assign work and monitor progress.
D
Starting Up a Project: to ensure the prerequisites for initiating the project are in place by answering the question 'Do we have a viable and worthwhile project?'
E
Closing a Project: to confirm that the product has been accepted.
Submit
You have used 0 of 1 attempt
Show Explanation
Next
▶