PRINCE2 Foundation: PRINCE2 Principles
Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
Read the scenario.

Riverside Library refurbishment: how the project is run The Project Board meets every Monday and approves each task before the team may start it. The Project Manager must ask the Executive before spending any money, even small amounts. No limits have been agreed for how far time or cost may vary before the Board must be told. Board members say they spend most of their week on project detail.

Which PRINCE2 principle is this project failing to apply?
Select one option.