The risk register for a warehouse project lists four threats.

Threat Description Probability Cost impact if it occurs
R1 Delivery of racking delayed 20% $50,000
R2 Software license price rises 60% $20,000
R3 Floor fails load test and must be rebuilt 10% $200,000
R4 Contractor shortage at peak season 50% $30,000

Using the expected value technique, which threat has the highest expected value?
Select one option.