PRINCE2 Foundation: Project Management Fundamentals and Introduction to PRINCE2
Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
Westbrook Hospital in Ohio is reviewing its current activities.

Westbrook Hospital: activity list 1. A team drawn from IT, nursing and finance has been brought together only to deliver a new electronic patient-records system. 2. The payroll office processes staff salaries every month using the same established procedure. 3. The new system will change the way nurses record and share patient information. 4. The IT helpdesk resets forgotten passwords whenever staff call.

Which two statements describe characteristics of a project, rather than business as usual?
Select one option.