PRINCE2 Foundation: Progress Practice
Question 1 of 5
Time left:
00:00
✓
Free PRINCE2 Foundation Q & A Practice
1 of 5 free PRINCE2 Foundation-standard exercises in this section
Study the graph for stage 2, at the end of week 5.
Stage 2 cost: budget $200,000 with tolerance of ±10% ($ thousands)
0
50
100
150
200
250
Wk 0
Wk 2
Wk 4
Wk 6
Wk 8
Wk 10
tolerance range at stage end
upper tolerance $220k
forecast $238k
Planned spend
Actual spend
Forecast
What should the Project Manager do?
Select one option.
A
Continue the stage and report the overspend in the End Stage Report.
B
Use the change budget to cover the extra cost without telling anyone.
C
Ask the Team Manager to submit an exception report to the business layer.
D
Wait until actual spend exceeds the tolerance before taking any action.
E
Raise an exception report to the Project Board, because the stage is forecast to exceed its cost tolerance.
Submit
You have used 0 of 1 attempt
Show Explanation