PRINCE2 Foundation: Plans Practice
Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
The four steps of PRINCE2's product-based planning technique are listed in a random order.

Code Planning step
P Create the product flow diagram
Q Write the project product description
R Write product descriptions for the products
S Create the product breakdown structure
Product breakdown structure: company website Company website Content Design Hosting service Page text Images Style guide Page templates Rectangles = products created by the project; ellipse = external product supplied from outside the project

In which order are the steps normally carried out?
Select one option.