The four steps of PRINCE2's product-based planning technique are listed in a random order.
| Code |
Planning step |
| P |
Create the product flow diagram |
| Q |
Write the project product description |
| R |
Write product descriptions for the products |
| S |
Create the product breakdown structure |
In which order are the steps normally carried out?
Select one option.