Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
Florence, the Project Manager for a new automated warehouse in Texas, has mapped stakeholders on a power and interest grid. The Chief Financial Officer approves the company's capital budgets but shows little interest in this project.

? Manage closely Monitor Keep informed Interest in the project → Power / influence → Chief Financial Officer Warehouse staff Operations Director Local residents

Which engagement approach is most appropriate for the Chief Financial Officer?
Select one option.