PRINCE2 Foundation: Business Case Practice
Question 1 of 5
Time left:
00:00
✓
Free PRINCE2 Foundation Q & A Practice
1 of 5 free PRINCE2 Foundation-standard exercises in this section
The timeline shows how the Business Case develops. The first step is hidden.
The Business Case through the project lifecycle
?
?
IP
Detailed
Business Case
in the PID
SB
Updated at each
stage end
DP
Board checks
viability at each
decision
CP / after
Benefits
reviewed
In which process is the
outline
Business Case first prepared, and who is accountable for it?
Select one option.
A
Initiating a Project; the Project Manager
B
Directing a Project; the Senior User
C
Managing a Stage Boundary; the Project Manager
D
Starting Up a Project; the Executive
E
Controlling a Stage; the Senior Supplier
Submit
You have used 0 of 1 attempt
Show Explanation
Next
▶