PRINCE2 Foundation: Business Case Practice
Question 1 of 5
Time left: 00:00
Free PRINCE2 Foundation Q & A Practice 1 of 5 free PRINCE2 Foundation-standard exercises in this section
The timeline shows how the Business Case develops. The first step is hidden.

The Business Case through the project lifecycle ? ? IP Detailed Business Case in the PID SB Updated at each stage end DP Board checks viability at each decision CP / after Benefits reviewed

In which process is the outline Business Case first prepared, and who is accountable for it?
Select one option.