Florence maps the key stakeholders of a U.S. state government’s tax-system program. Stakeholder S2 is the state budget director, who has authority to freeze program funding but has shown little interest in program detail.

Keep satisfiedManage closelyMonitorKeep informedInterest →Power →lowhighS1S2S3S4


Which engagement approach is most appropriate for S2?
Select one option.
You have used 0 of 1 attempt