Charles maintains the integrated master schedule for a U.S. bank’s digital-lending program. Durations and dependencies are shown (week 0 is the program start).
Component
Duration
Can start when…
A Data platform
12 weeks
week 0
B Mobile app
12 weeks
week 4
C Integration test
6 weeks
A and B are both finished
D Staff training
4 weeks
C is finished
E Regulatory approval
10 weeks
A is finished
Go-live
—
D and E are both finished
Component B now reports a 3-week delay to its finish. If nothing else changes, in which week will the program go live?