Charles maintains the integrated master schedule for a U.S. bank’s digital-lending program. Durations and dependencies are shown (week 0 is the program start).

048121620242832A Data platformB Mobile appC Integration testD Staff trainingE Reg. approvalgo-live: week 26

ComponentDurationCan start when…
A Data platform12 weeksweek 0
B Mobile app12 weeksweek 4
C Integration test6 weeksA and B are both finished
D Staff training4 weeksC is finished
E Regulatory approval10 weeksA is finished
Go-live—D and E are both finished


Component B now reports a 3-week delay to its finish. If nothing else changes, in which week will the program go live?