PgMP: Program Definition and Initiation
Question 1 of 5
Time left:
00:00
✓
Free PgMP Q & A Practice
1 of 5 free PgMP-standard exercises in this section
Charles is preparing the charter for a U.S. state agency’s permit-modernization program. His draft is shown below.
Draft program charter
✓
Program vision
✓
Strategic alignment
✓
Scope and key components
✓
Assumptions and constraints
✓
High-level risks
✓
Timeline and milestones
✓
Resource and funding estimate
✓
Stakeholder considerations
(section 9 blank)
Which element must Charles add before the charter is submitted for authorization?
Select one option.
A
Detailed schedules for each component project
B
A work breakdown structure for every component
C
Named assignments for each team member
D
The expected program benefits and how success will be measured
E
The final terms of each vendor contract
Submit
You have used 0 of 1 attempt
Show Explanation
Next
▶