PgMP: Closure, Transition, and Value Delivery
Question 1 of 5
Time left:
00:00
✓
Free PgMP Q & A Practice
1 of 5 free PgMP-standard exercises in this section
Charles is preparing to close a three-year U.S. public-health data program. Several of its benefits will keep growing for another four years.
Program closure checklist
✓
All components closed and accepted
✓
Transition to operations complete
✓
Benefit owners hold sustainment plans
✓
Contracts closed, invoices settled
✓
Lessons learned recorded
!
Governance approval to close
What should Charles do next?
Select one option.
A
Present the closure recommendation and evidence to the program governance board and obtain formal approval to close
B
Keep the program open until all benefits have been fully realized in four years’ time
C
Release the program team and archive the files; formal approval is not needed once the checklist is complete
D
Start the next program using the remaining budget before closing this one
E
Ask the PMO to sign off the closure on behalf of the sponsor