Charles, a newly appointed PMO director at a U.S. telecommunications company, reviews six approved initiatives. The diagram shows their relationships.
feeds
feeds
interface
enables
P
Billing system
upgrade
Q
Customer portal
rebuild
R
Data migration
to new CRM
S
Contact-center
retraining
T
Office lease
renewal
U
Annual payroll
audit
P, Q, R, S all support the retention target
Which grouping is the most appropriate to manage as a
program
?
Select one option.
A
All six initiatives, because they are funded from the same annual budget
B
T and U, because they are both corporate support activities
C
P and Q only, because they share a technical interface
D
P, Q, R and S, because they are interdependent and together deliver a benefit none can deliver alone
E
Each initiative separately as a standalone project, managed by a single portfolio manager
Submit
You have used 0 of 1 attempt
Show Explanation
Next
▶