PgMP: Benefits Management
Question 1 of 5
Time left:
00:00
✓
Free PgMP Q & A Practice
1 of 5 free PgMP-standard exercises in this section
Florence is building a benefit dependency network for a U.S. manufacturer’s sales-transformation program.
CRM system
installed
Sales training
delivered
?
Sales cycle
45 → 30 days
+$3M yearly
revenue
Objective: grow
market share 5%
enablers
business change
outcome
benefit
Which item belongs in the position marked “?”?
Select one option.
A
A new CRM software license
B
Revenue increases by
$3 million
per year
C
Approval of a
$200,000
training budget
D
Sales staff use a shared view of each customer in every sales call
E
Market share grows by 5%
Submit
You have used 0 of 1 attempt
Show Explanation
Next
▶