A purchasing manager, Margaret Hollis, must choose one supplier for a component. The table lists each supplier's quoted price per unit, defect rate, lead time, and monthly capacity.
| Supplier |
Price per unit |
Defect rate |
Lead time (days) |
Capacity (units/month) |
| Ashford |
$12.40 |
1.2% |
12 |
6,000 |
| Brookline |
$11.90 |
2.0% |
10 |
8,000 |
| Carlisle |
$12.10 |
1.4% |
16 |
7,000 |
| Dunmore |
$12.25 |
0.8% |
13 |
4,500 |
| Kingsley |
$12.36 |
1.5% |
14 |
5,000 |
| Westbury |
$12.45 |
0.4% |
11 |
5,500 |
The supplier must have a defect rate of at most \(1.5\%\), a lead time of at most \(14\) days, and a capacity of at least \(5{,}000\) units per month. Defective units are discarded, so the relevant cost is the
price per non-defective unit. Which qualifying supplier has the lowest price per non-defective unit?
Select one option.